Accreditation

Grant of Accreditation

A large number of applications will be received for grant of accreditation by Accreditation Branch through out the year. The grant of accreditation is a continuous process and requires about 2-3 months to complete it. It involves scrutiny of applications forms consideration of the applications in Screening Board, constitution of inspection teams, visit to the schools for inspection and final clearance from Accreditation Advisory Committee.
A time schedule for processing the application form will help to streamline, monitor and disseminate the information whenever required. The schedule for processing of application form is submitted as below :

I. Applications received in January/February/March

Screening Board meetingBy 07th of April
Inspection – 60 days 10th April-10th June
AAC & release of Accreditation Letter15-25th June

II. Application received in April/May/June

Screening Board meetingBy 07th of July
Inspection – 60 days 10th July - Sep 10th
AAC & release of Accreditation Letter15-25th Sept

III. Application received in July/August/September

Screening Board meetingBy 07th of Oct
Inspection – 60 days 10th Oct-10th December
AAC & release of Accreditation Letter15-25th December

IV. Application received in October/November/December

Screening Board meetingBy 07th of Jan
Inspection – 60 days 10th Jan - 10th March
AAC & release of Accreditation Letter15-25th March